First Solar Inc. (FSLR), the biggest U.S. solar manufacturer, halted
deliveries to the world’s largest photovoltaic power plant, which it’s
building in Arizona, because construction is ahead of schedule and the
company must slow down to meet contractual milestones.
First Solar won’t ship additional modules until January to the $1.8 billion
Agua Caliente project and won’t install panels currently sitting on the
ground at the site, said Fred Pech, the power plant’s construction manager.
The solar farm is scheduled for completion at the end of 2013 and is 85
percent built.
The company, based in Tempe, Arizona, accelerated construction on Agua
Caliente this year to use panels it produced as far away as Germany and
Malaysia amid a global glut. Now it will probably divert shipments to other
projects to prevent inventories from piling up, said Aaron Chew, an analyst
at Maxim Group LLC in New York.
First Solar delivered panels to the project “because it was more profitable
,” Chew said today in a telephone interview. “They overdid Agua Caliente.
” Expanding its focus on power plants helped make First Solar the only
profitable solar company in the Bloomberg Industries Global Large Solar
Index in the the second quarter.
The shutdown probably won’t affect First Solar’s earnings this year, Chew
said. “However, it does highlight the extent to which they’re pulling
things forward, with bigger risks in 2013 and 2014.”
The decision to wind down installation for this year may be “related to
contractors and construction crew, perhaps minimum number of hours,” Chew
said.
Last Module
“We installed the last module for block 10 on Monday,” Pech said in an
interview yesterday a the plant, located on 2,400 acres of desert about 120
miles (193 kilometers) west of Phoenix. There are two more blocks of panels
planned for the site and “we could be done by the end of this year, but we
’re way ahead of schedule.”
Dozens of boxes of unused panels are piled up at the site, covered in blue
tarps to prevent degradation over the next four months while First Solar
waits to resume installation.
With 85 percent of its panels installed, Agua Caliente has about 247
megawatts of capacity, making it the the world’s largest operating solar
farm. PG&E Corp. (PCG)’s Pacific Gas & Electric Co. is buying the power
under a 25-year agreement.
The power plant was generating 249 megawatts of electricity yesterday at 11:
30 a.m. local time and its output has reached as much as 251.3 megawatts
under ideal sunlight conditions, Pech said.
The project received a $967 million loan guarantee from the U.S Energy
Department. Phone calls and e-mails to Damien LaVera, an agency spokesman,
weren’t immediately returned.
First Solar shares fell 10 percent to $21.73 at 10:58 a.m. in New York.
The plant is owned by NRG Energy Inc. (NRG) and MidAmerican Energy Holdings
Co. Phone calls and e-mails to Lori Neuman, an NRG spokeswoman, weren’t
immediately returned today.
To contact the reporter on this story: Christopher Martin in New York at
deliveries to the world’s largest photovoltaic power plant, which it’s
building in Arizona, because construction is ahead of schedule and the
company must slow down to meet contractual milestones.
First Solar won’t ship additional modules until January to the $1.8 billion
Agua Caliente project and won’t install panels currently sitting on the
ground at the site, said Fred Pech, the power plant’s construction manager.
The solar farm is scheduled for completion at the end of 2013 and is 85
percent built.
The company, based in Tempe, Arizona, accelerated construction on Agua
Caliente this year to use panels it produced as far away as Germany and
Malaysia amid a global glut. Now it will probably divert shipments to other
projects to prevent inventories from piling up, said Aaron Chew, an analyst
at Maxim Group LLC in New York.
First Solar delivered panels to the project “because it was more profitable
,” Chew said today in a telephone interview. “They overdid Agua Caliente.
” Expanding its focus on power plants helped make First Solar the only
profitable solar company in the Bloomberg Industries Global Large Solar
Index in the the second quarter.
The shutdown probably won’t affect First Solar’s earnings this year, Chew
said. “However, it does highlight the extent to which they’re pulling
things forward, with bigger risks in 2013 and 2014.”
The decision to wind down installation for this year may be “related to
contractors and construction crew, perhaps minimum number of hours,” Chew
said.
Last Module
“We installed the last module for block 10 on Monday,” Pech said in an
interview yesterday a the plant, located on 2,400 acres of desert about 120
miles (193 kilometers) west of Phoenix. There are two more blocks of panels
planned for the site and “we could be done by the end of this year, but we
’re way ahead of schedule.”
Dozens of boxes of unused panels are piled up at the site, covered in blue
tarps to prevent degradation over the next four months while First Solar
waits to resume installation.
With 85 percent of its panels installed, Agua Caliente has about 247
megawatts of capacity, making it the the world’s largest operating solar
farm. PG&E Corp. (PCG)’s Pacific Gas & Electric Co. is buying the power
under a 25-year agreement.
The power plant was generating 249 megawatts of electricity yesterday at 11:
30 a.m. local time and its output has reached as much as 251.3 megawatts
under ideal sunlight conditions, Pech said.
The project received a $967 million loan guarantee from the U.S Energy
Department. Phone calls and e-mails to Damien LaVera, an agency spokesman,
weren’t immediately returned.
First Solar shares fell 10 percent to $21.73 at 10:58 a.m. in New York.
The plant is owned by NRG Energy Inc. (NRG) and MidAmerican Energy Holdings
Co. Phone calls and e-mails to Lori Neuman, an NRG spokeswoman, weren’t
immediately returned today.
To contact the reporter on this story: Christopher Martin in New York at
H*1
4 楼
should I short if I have no position, thanks!
i*e
5 楼
HP Pavilion 17-E020US不错,不知道会不会有人收
T*C
6 楼
真是扶不起
billion
manager.
【在 y*******o 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: First Solar Inc. (FSLR), the biggest U.S. solar manufacturer, halted
: deliveries to the world’s largest photovoltaic power plant, which it’s
: building in Arizona, because construction is ahead of schedule and the
: company must slow down to meet contractual milestones.
: First Solar won’t ship additional modules until January to the $1.8 billion
: Agua Caliente project and won’t install panels currently sitting on the
: ground at the site, said Fred Pech, the power plant’s construction manager.
: The solar farm is scheduled for completion at the end of 2013 and is 85
: percent built.
: The company, based in Tempe, Arizona, accelerated construction on Agua
billion
manager.
【在 y*******o 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: First Solar Inc. (FSLR), the biggest U.S. solar manufacturer, halted
: deliveries to the world’s largest photovoltaic power plant, which it’s
: building in Arizona, because construction is ahead of schedule and the
: company must slow down to meet contractual milestones.
: First Solar won’t ship additional modules until January to the $1.8 billion
: Agua Caliente project and won’t install panels currently sitting on the
: ground at the site, said Fred Pech, the power plant’s construction manager.
: The solar farm is scheduled for completion at the end of 2013 and is 85
: percent built.
: The company, based in Tempe, Arizona, accelerated construction on Agua
S*r
7 楼
有搞头, 新出的几款笔记本 有很大的折扣
t*9
8 楼
还以为要破产
billion
manager.
【在 y*******o 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: First Solar Inc. (FSLR), the biggest U.S. solar manufacturer, halted
: deliveries to the world’s largest photovoltaic power plant, which it’s
: building in Arizona, because construction is ahead of schedule and the
: company must slow down to meet contractual milestones.
: First Solar won’t ship additional modules until January to the $1.8 billion
: Agua Caliente project and won’t install panels currently sitting on the
: ground at the site, said Fred Pech, the power plant’s construction manager.
: The solar farm is scheduled for completion at the end of 2013 and is 85
: percent built.
: The company, based in Tempe, Arizona, accelerated construction on Agua
billion
manager.
【在 y*******o 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: First Solar Inc. (FSLR), the biggest U.S. solar manufacturer, halted
: deliveries to the world’s largest photovoltaic power plant, which it’s
: building in Arizona, because construction is ahead of schedule and the
: company must slow down to meet contractual milestones.
: First Solar won’t ship additional modules until January to the $1.8 billion
: Agua Caliente project and won’t install panels currently sitting on the
: ground at the site, said Fred Pech, the power plant’s construction manager.
: The solar farm is scheduled for completion at the end of 2013 and is 85
: percent built.
: The company, based in Tempe, Arizona, accelerated construction on Agua
R*a
10 楼
也不是什么非常利空的消息吧?
S*r
11 楼
Acer V5-571P-6407 还可以。还有几款不记得了, 去店里看看
m*x
13 楼
可以和 10 off 40 叠用么?
y*o
14 楼
if you could, but there is no share to short when I try to short [email protected]
I did buy the 22 puts expired tomorrow. It is highly risk, but I would like
to take the risk.
This news will pull the trigger and it going go to below 20 today and also
gap down tomorrow, since it has so huge short amount.
【在 H**********1 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: should I short if I have no position, thanks!
I did buy the 22 puts expired tomorrow. It is highly risk, but I would like
to take the risk.
This news will pull the trigger and it going go to below 20 today and also
gap down tomorrow, since it has so huge short amount.
【在 H**********1 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: should I short if I have no position, thanks!
y*e
15 楼
这个呢?
Asus S400CA-RSI5T18 14" Touch Screen Laptop
Asus S400CA-RSI5T18 14" Touch Screen Laptop
m*i
16 楼
Good Call.
like
【在 y*******o 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: if you could, but there is no share to short when I try to short [email protected]
: I did buy the 22 puts expired tomorrow. It is highly risk, but I would like
: to take the risk.
: This news will pull the trigger and it going go to below 20 today and also
: gap down tomorrow, since it has so huge short amount.
like
【在 y*******o 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: if you could, but there is no share to short when I try to short [email protected]
: I did buy the 22 puts expired tomorrow. It is highly risk, but I would like
: to take the risk.
: This news will pull the trigger and it going go to below 20 today and also
: gap down tomorrow, since it has so huge short amount.
m*r
17 楼
高税州买啥?
d*5
19 楼
神医吼一声,俺就去扫了。
S*r
26 楼
hp 17-e020us 貌似不错。不知道是不是2270us的升级版。
S*r
31 楼
要不搞台X2自用?
b*g
35 楼
旧的us rebate已经过期了,新的好像找不出来
d*1
38 楼
店里都要开苞 啥都没戏
S*r
43 楼
没有form的可以用这个啊
https://h41201.www4.hp.com/WMCF.Web/us/en/promotion/7314/Details/
【在 f****g 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: 这次有些怪,我周日买了7246us,2243us
: 7246us有新rebate,2243us就不出
https://h41201.www4.hp.com/WMCF.Web/us/en/promotion/7314/Details/
【在 f****g 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: 这次有些怪,我周日买了7246us,2243us
: 7246us有新rebate,2243us就不出
f*g
44 楼
这要cut upc了,神医就没法fba了
【在 S***r 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: 没有form的可以用这个啊
: https://h41201.www4.hp.com/WMCF.Web/us/en/promotion/7314/Details/
【在 S***r 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: 没有form的可以用这个啊
: https://h41201.www4.hp.com/WMCF.Web/us/en/promotion/7314/Details/
f*i
46 楼
3291014, new rebate offer for HP us laptop
a*g
48 楼
不晓得买什么好。早上随便下了一个,到现在都差不了status,是不是被block了啊。
c*2
49 楼
Toshiba L55-A5284 was available 1 hour ago at $499 and I added to cart it
was $650 (which is $600 after 50 MIR) so I didn't continue.
what happen to the $101 coupon?
Just right now I visit the page again and it is "currently out of stock"
was $650 (which is $600 after 50 MIR) so I didn't continue.
what happen to the $101 coupon?
Just right now I visit the page again and it is "currently out of stock"
c*2
50 楼
answer myself. coupon expired yesterday. No wonder the price at the check
out is $151 more than the advertised $499. ($101 instant coupon + $50 MIR)
【在 c**2 的大作中提到】![](/moin_static193/solenoid/img/up.png)
: Toshiba L55-A5284 was available 1 hour ago at $499 and I added to cart it
: was $650 (which is $600 after 50 MIR) so I didn't continue.
: what happen to the $101 coupon?
: Just right now I visit the page again and it is "currently out of stock"
out is $151 more than the advertised $499. ($101 instant coupon + $50 MIR)
【在 c**2 的大作中提到】
![](/moin_static193/solenoid/img/up.png)
: Toshiba L55-A5284 was available 1 hour ago at $499 and I added to cart it
: was $650 (which is $600 after 50 MIR) so I didn't continue.
: what happen to the $101 coupon?
: Just right now I visit the page again and it is "currently out of stock"
相关阅读
Two pharm picks看看今天与昨天的精准预测船运EXM到哪里去了?WOW, BTU 14.XX私拿下周突破60?说一千,道一万。。。。两房上亏费的都过来排包子好了伤疤忘了疼aapl crashingeven you don't have big money, invest all you have!Thesis: how much will the chinese market affect the market of USA?long SPY@ 160What happened to YELP?Federer lost too煤可以买不普京强硬 美国主动“降温” 对俄罗斯态度软化ZZ艹塌麻,三星做广告用词真让人呕吐猴哥在拿板砖拍鱼USA is so naughty!2房不可能解散